This thread started in 2012; so we're about 9 years on...........

It took about 6 years to get a shovel in the ground.

It took 1 year, 8 months from the arrival of shoring to the arrival of the crane.

4-5 months to reach grade

About 2 months to get the 1st floor up I think, based on the pics.

Now we're up at the 7th floor roughly 4 months later.

Glad to see the pace has accelerated!

At the current rate, we should be topped out by the end of summer and substantial completion by year end.
 
This thread started in 2012; so we're about 9 years on...........

It took about 6 years to get a shovel in the ground.

It took 1 year, 8 months from the arrival of shoring to the arrival of the crane.

4-5 months to reach grade

About 2 months to get the 1st floor up I think, based on the pics.

Now we're up at the 7th floor roughly 4 months later.

Glad to see the pace has accelerated!

At the current rate, we should be topped out by the end of summer and substantial completion by year end.
Are you saying it's going to continue accelerating so by this time next year we'll have the next supertall?!
 