Work may seem slow at the One, but lots of foundation work has taken place since I’ve started working on site a few weeks ago. Concrete pour for the 5th floor transfer slab has been the top focus and is now complete. The base for the tower elevators shafts will also sit on the 5th floor. Frame installations on the southwest elevation portion of the project, along with panel installations for the atrium are also currently being implemented. Columns extending to level 9 are currently being installed as well.