Pouring elevator core elements today.
I'm getting serious Thaivic, time for you to move up a couple floors!
Intriguing, Mr. Bond...There is a video on LinkedIn of the self climbing formwork for the core making its first move up one level:
Sign Up | LinkedIn
500 million+ members | Manage your professional identity. Build and engage with your professional network. Access knowledge, insights and opportunities.www.linkedin.com
I will put in the request...lolI'm getting serious Thaivic, time for you to move up a couple floors!
/s just in case
Alright, this might be a stupid question, but I will ask nonetheless.
Are different types of concrete used for different parts of the tower? Like floor plates vs. elevator core vs. floor corners vs. mega column filler etc?
Thanks in advance to whoever answers!
Temporary one...until they get the one in the core up to speed?Any idea what this is? I assumed it was a new external lift at first until I remembered they’re building elevators in the core.
It's possible the core lifts will only be used when they get above the hotel levels. Thinking they'll want to finish out the retail and hotel levels while they build the residences? So you have (the existing) exterior lift that goes up to the pool level deck, then another one up to the beginning of the residences? You don't want workers and materials having to go through the hotel to the core lifts...Temporary one...until they get the one in the core up to speed?
correct it's called a HoistAny idea what this is? I assumed it was a new external lift at first until I remembered they’re building elevators in the core.
: @Benito
View attachment 423721
Yep, I knew that, thanks. My question is more specifically: why are they installing it when they’re putting climbing construction elevators in the core? I think @UpwithOlives has a good answer.correct it's called a Hoist