Part 1 of 3 taken on May 11, 2023:

Yonge side:

IMG_8470.jpeg
IMG_8471.jpeg
IMG_8472.jpeg
IMG_8473.jpeg
IMG_8474.jpeg
IMG_8475.jpeg
IMG_8476.jpeg
IMG_8477.jpeg
IMG_8478.jpeg
 
Photos taken today, Friday (May 12). Since my last set of photos a week ago, the 4th level of hangers placed on the west side with the corner sections adding a floor each pretty well, and another level on top poured - 28th? 29th? I was told a few weeks ago that the truss for the west side might be delayed because of a conflict with TTC work. Not sure why that is so, but clearly delays there, as nine of those hanging platforms are to be placed on each truss, and none have been placed since I photographed the fifth one on the east side being installed a few weeks ago.

So... mostly a bunch of wide shots this week...

Plus... latest "time-lapse" photo included from my Flickr album here:


UTIMG_5667.jpg
UTIMG_5690.jpg
UTIMG_5776.jpg


UTIMG_5609a.jpg

UTIMG_5705.jpg


UTIMG_5654.jpg
 

Attachments

  • UTIMG_5609.jpg
    UTIMG_5609.jpg
    295.9 KB · Views: 637
Last edited:
Photos taken today, Friday (May 12). Since my last set of photos a week ago, the 4th level of hangers placed on the west side with the corner sections adding a floor each pretty well, and another level on top poured - 28th? 29th? I was told a few weeks ago that the truss for the west side might be delayed because of a conflict with TTC work. Not sure why that is so, but clearly delays there, as nine of those hanging platforms are to placed on each truss, and none have been placed since I photographed the fifth one on the east side being placed a few weeks ago.

So... mostly a bunch of wide shots this week...

Plus... latest "time-lapse" photo included from my Flickr album here:


View attachment 476804View attachment 476803View attachment 476801View attachment 476800View attachment 476802View attachment 476805

28th poured and 29th being prepared.
 

Back
Top