Stage one
Completion of early works (demolition, abatement and other preparatory work)
Start of excavation ("dig down") under the York concourse, VIA concourse and part of the Bay concourse
Start of upgrades to mechanical and electrical systems
Start of restoration work on the exterior façade
Completion of loading dock
Completion of the Bay and York teamways within the viaduct structure
Completion of West Wing
Completion of VIA Panorama Lounge
Completion of two new bike stations
Completion of York concourse
Completion of lower retail level on west side
Completion of first part of North/West PATH across Front St.
Stage two
Continue with dig down under the Bay concourse
Continue with construction of the new Bay concourse
Construction of a retail level below the Bay concourse (part of the future Bay promenade)
Restoration of VIA concourse
Continuation of the restoration/repair of the exterior façade and initiate work within the Great Hall
Restoration of Front St. West moat and York St. moat and installation of moat covers
Stage three
Renovation of the first floor of the East Wing
Multi-phased dig down below the East Wing for the completion of the Bay promenade retail level
Completion of the repair/restoration of the Great Hall
Complete the repair/restoration of the exterior facade
Reconstruction of the Front St. East moat and installation of a moat cover including removal of the steps down to the TTC
Restoration of Bay St. moat and installation of a moat cover
Completion of the NW Path to Wellington St.