November 2022 Market Update release earlier today. Relevant YNSE information see below:
Advance Tunnel procurement will be commence early next year. No timeline on the Stations, Rail and Systems yet.
Project Yonge North Subway Extension - Advance Tunnel*
Project Phase Pre-Procurement
Model DBF
PDC/TA Procurement Awarded
Issue RFQ Jan - Mar 2023
Issue RFP Apr - Jun 2023
Contract Execution Apr - Jun 2024
Design & Construction Cost $1B - $2B
Project Yonge North Subway Extension - Stations, Rail and Systems*
Project Phase Pre-Procurement
Model TBD
PDC/TA Procurement Awarded
Issue RFQ TBD
Issue RFP TBD
Contract Execution TBD
Design & Construction Cost $2B - $4B
* Metrolinx and Infrastructure Ontario continue to review these projects for the most suitable staging and sequencing in recognition of continuing market feedback and other recently issued procurements to market.
Source - https://www.infrastructureontario.c...et_Update/Market Update_11212022_FINAL_EN.pdf
Advance Tunnel procurement will be commence early next year. No timeline on the Stations, Rail and Systems yet.
Project Yonge North Subway Extension - Advance Tunnel*
Project Phase Pre-Procurement
Model DBF
PDC/TA Procurement Awarded
Issue RFQ Jan - Mar 2023
Issue RFP Apr - Jun 2023
Contract Execution Apr - Jun 2024
Design & Construction Cost $1B - $2B
Project Yonge North Subway Extension - Stations, Rail and Systems*
Project Phase Pre-Procurement
Model TBD
PDC/TA Procurement Awarded
Issue RFQ TBD
Issue RFP TBD
Contract Execution TBD
Design & Construction Cost $2B - $4B
* Metrolinx and Infrastructure Ontario continue to review these projects for the most suitable staging and sequencing in recognition of continuing market feedback and other recently issued procurements to market.
Source - https://www.infrastructureontario.c...et_Update/Market Update_11212022_FINAL_EN.pdf