someMidTowner
¯\_(ツ)_/¯
The former Second Cup at the northwest corner of Mt. Pleasant and Eglinton is currently surrounded by a scaffold with trash chutes installed in the upper windows. Looks like the gutting has begun.
I can't believe this thing is nearly 50% complete. It's a good feeling
I'm curious - what metric are you using to measure completion?
The Crosstown web site - whose information is as of the end of last year - shows a spend of 17% at that point, and construction less than 20% along on the AFP portion.
http://www.thecrosstown.ca/progress/funding
- Paul
Call me pessimistic and pedantic, but with so much left to do there I'd feel happier if we knew more about the schedule - before it shifts.
When will the eastern above ground portion begin construction, and eventually be full functional?
Construction on the surface begins December 2017. Construction on the surface concludes November 2019. Revenue service begins September 2021
Delivery of light rail vehicles to start 2022?
Sorry, couldn't resist.
How dare you say that? BBD doesn't deserve that.
You're being far too optimistic--2025 might be more reasonable.
![]()
No, no, no. Vehicle delivery will surely commence during November 2022. But the vehicles will be delivered on average once every four months, with assurances from Bombardier that they can still somehow make a 2019 deadline for delivery of all the vehicles.