Monarch Butterfly
Superstar
Fire trucks can drive on artificial grass, on concrete.
I believe that any plans for grass was cancelled long ago. Correct me if I am wrong however.
4 trees and they need to make a special announcement. Maybe they should be forced to have an EA Amendment because the tress are a bit taller than when approval was first granted.OMG!! North York had (past tense) trees???
Tree Removal on Eglinton Avenue East at the West Don River Bridge
From link.
In support of the continued construction of the Crosstown LRT tracks and guideway (dedicated transit lane) in the centre of Eglinton Avenue East, tree removal is required for four (4) trees in close proximity to the construction zone at the West Don River Bridge.Tree protection measures will be in effect, and environmental personnel will be on site to ensure tree removal and protection is completed in accordance with regulatory requirements. All removals have been approved by the City of Toronto and Toronto and Region Conservation Authority (TRCA). Upon the completion of the Crosstown LRT, new trees will be planted in place of the removed ones.Tree removal is anticipated to begin as early as September 3, 2019, and continue for one (1) day.
TIMING
- Work is expected to occur from 7:00 a.m. to 11:00 p.m.
- Tree removal in this area will begin as early as September 3, 2019.
- The contractor may not always work during the permitted hours, but may do so at its discretion.
- Work may be rescheduled due to weather conditions or unforeseen circumstances.
WHAT TO EXPECT
- Removal of 4 treeson the south side of Eglinton Avenue East at the West Don River Bridge.
- Residents and businesses nearby should anticipate noise from chainsaws and wood chippers for the removal of trees.
- In addition to construction activity, residents can expect to see equipment and material storage within designated work zones.
Fire trucks can drive on artificial grass, on concrete.
The walls and centre walls that support the roof of the portal are in place with the first section of the roof pour on the west side of Kennedy. The rest of the roof on the west side of Kennedy should be done in Sept. Back filling could start in Sept along filling in the roof area after the roof is pour..I live in this area and finally we can breath a sigh of relief that all the MAJOR construction is done. They are still putting in track but they are no longer ripping up the road and relocating things.
With the exception of Kennedy Station work is coming along nicely. It would however be nice if they could complete work on the portal.
Do you guys think this project will be finished on time? The contractually agreed revenue service start date is just two years from today (give or take 30 days). Most of the underground stations visually look nowhere close to completion. I would’ve expected we’d see some substantial completion of surface structures right now, but so far I haven’t seen anything.
The progress of Bathurst Station in particular has been amazingly slow. That intersection has been torn up for 5 years now, and the station is still just a giant pit in the ground. Indeed, if I remember correct, Bathurst is the least-completed station on the line
Nevertheless, it’s amazing to see something we’ve discussed for 13 years now finally all come together. I don’t think I’ve yet internalized that Toronto is about to get its first major new rapid transit line in 60 years.
Do you guys think this project will be finished on time? The contractually agreed revenue service start date is just two years from today (give or take 30 days).
Raping transit?Isn't the Sheppard line new raping transit ??
I keep telling myself that they're on time, I don't think the street service portion will take all that long to complete. A lot of it is almost completed now if you ask me. As far as the stations go, I don't think those will take all that long as well. Most of them have already started to be building up towards grade now. Mount Dennis and keesedale should be completed by this year. A lot of work could be done in 2yrs, you could build a high-rise with underground parking from start to finish in 2 years, so yeah I think they will be done on time, that could be me being nieve and optimistic tho.
It's interesting to go back and see where TYSSE was two years before opening day. From a quick scan back to around Message 4545 in the TYSSE thread, in December 2015 all the station pours were complete and structural steel was being erected for the above ground portion of the stations.
By that standard, Crosstown is behind. It's possible its stations are a little less complicated, but all the same subsystems will need to be there. And with some of the stations nothing but holes, the installation of power, signalling, data, escalators and elevators, HVAC, etc etc is that much farther behind.
Personally I won't sleep until they get all the structural work at Cedervale and Yonge done, and we know there hasn't been an "oops" with the Line 1 subway structure. That strikes me as the most risky part of the project, and we aren't there yet. The other holes are dug, at least, and concrete pours seem to be progressing at most. Pouring the roofs and backfilling is (relatively) straightforward. The mined stations, however, are a big question mark.
- Paul




