Sept 10
Been lackey a Daisey the past week that I haven't been working on my backlog as well getting out on the nice days to add more photos until today.
Next to nothing has been done to the corridor since my last visited with a few exceptions. PC roof looks the same with nothing been added to the forms in place on Aug 27
Dundas intersection to be close Sept 16 based on a sign I saw going by it to fast to read all of it.
John St close Sept 5 to the 20th.
Work on Watergarden Intersection has yet to start.
Eastbound ramp to Hurontario for the 401 is close and don't know when that happen. It dug out and that it so far.
They have fixed the tracks at Animal and have pour concrete for it. Until the rails are splice at Matheson Station and area, concrete can't be pour for the tracks that are finally in place.
They have started to lay the ties at Northflight Intersection with a lot more to be place. Tracks are being installed to connect the OMSF to Northflight with once section having the base pour for the tracks. Top coat could be done by the next Friday.
At the rate work is taking place, The test bed maybe ready by Q2 2024 with service starting Q3 2025 to Q2 2026, The end of 2024 will come and go before completion of the line as plan.
A few shots not tag or fix or up on my site