What do you think of this project?


  • Total voters
    28
The replacement cab has been installed. Crew boss thinks they will be done today. A few other photos b/c I was bored!

CraneTop-2_4165.jpg113 St monkey bars_4158.jpgNew crane shaft_4153.JPGNew crane cab positioning_4156.JPG
 
Kinda surprised they even bothered installing a new tower crane. They've only got five more stick built floors to go and they have plenty of laydown space. Why not opt for one of those self erecting cranes like the one on the Abbey Park job?

Maybe they got this green one real cheap. Frankly it looks like it's from Soviet-era Belarus...
 
Love to colour/look. I wonder if it was brought to the area for this and future projects?
It was brought in because the previous crane extended too far over the neighbour's property and Westrich Pacific thought they wouldn't notice, and then tried to pretend that the neighbour had signed off on it.
 
^it does not work like that. Crane swing and air rights are formally considered and approved.
 
^it does not work like that. Crane swing and air rights are formally considered and approved.
Yeah, and they exceeded their air rights by about 6m resulting in a stop work order after the neighbour called them on it.
 

Back
Top