| | | 2025Q3 Status | | | | 2025Q4 Status |
| Portfolio | Line | Project | Prequalification | RFP | Awarded | MERX | Estimated RFP Date |
| GO Expansion | Stouffville | Mount Joy Station Improvements, Passing Track and Signals: Construction of passing track, a new side platform and associated infrastructure, and signals work including installation of new turnback signal near Stouffville GO. | Dec-22 | Upcoming 2025Q4 | | | 2026Q4 (delayed one year) |
| GO Expansion | Stouffville | Stouffville Existing Station Renovations: Upgrades to various existing GO stations in the Stouffville corridor including civil work (e.g., parking lot improvements, bus loop restoration, station building retrofits and platform upgrades including
accessibility upgrades). | Dec-22 | Upcoming 2026Q1 | | | 2026Q1 (unchanged) |
| GO Expansion | Stouffville | Kennedy GO Station: West Platform Extension and Trackwork. | TBD | TBD | | | Project Removed |
| GO Expansion | Barrie | Barrie Existing Station Renovations: Upgrades to various existing GO stations in the Barrie corridor including civil work (e.g., parking lot and bus loop improvements, station building retrofits and platform upgrades). | Dec-22 | Upcoming 2026Q1 | | | 2026Q1 (unchanged) |
| GO Expansion | Barrie | West Toronto Rail Path Extension (South of Dundas Street on the Barrie Corridor): Grading work, along with construction of four new, multi-use path bridges and several community connections. | TBD | TBD | | | 2026Q2 (new date) |
| GO Expansion | Barrie | Bradford Station: West Platform Construction and Layover Modification. | TBD | TBD | | | Project Removed |
| GO Expansion | LSE | Lakeshore East Existing Station Renovations: Upgrades to various existing GO stations in the Lakeshore East corridor including civil work (e.g., parking lot and bus loop improvements, station building retrofits and platform upgrades
including accessibility upgrades). | Dec-22 | Upcoming 2026Q1 | | MERX Project Tender July 2025 | 2026Q1 (unchanged) |
| GO Expansion | LSW | Lakeshore West Existing Station Renovations: Upgrades to various existing GO stations in the Lakeshore West corridor including civil work (e.g., parking lot improvements, bus loop restoration, station building retrofits and platform
upgrades including accessibility upgrades). | Dec-22 | Upcoming 2026Q1 | | | 2026Q1 (unchanged) |
| GO Expansion | LSW | Niagara Falls Layover Facility: Construction of a single-track layover facility for train storage, along with signals and track work. | TBD | TBD | | | Project Removed |
| GO Expansion | RH | Oriole GO Station Relocation: Improved station access, customer safety and customer experience. | TBD | TBD | | | Project Removed |
| GO Expansion | KI | Kitchener Line Extension | Guelph Subdivision Package 4: Track and signals work, platform work, grading, drainage, and utility relocations in support of Kitchener GO service extension. | Apr-24 | Upcoming 2026Q1 | | | 2026Q2 (delayed one quarter) |
| GO Expansion | KI | Kitchener Central Transit Hub: Construction of a GO station that is part of multimodal transportation hub in the Waterloo Region. Construction of track realignment, switch, station platforms, tunnels and associated civil works to support a Region-led initiative for a new multi-modal transit hub in Waterloo Region. | Dec-25 | Upcoming 2026Q1 | | MERX Prequalification November 2025 | 2026Q2 (delayed one quarter) |
| GO Expansion | KI | Mount Pleasant GO Station Modifications: Renovations including removal of the north platform to create space for a future track and modifications to existing tunnels, north stairs, and elevator. | N/A | TBD | | | 2027Q4 (new date) |
| GO Expansion | KI | Kitchener Extension | Guelph Subdivision Package 2A: Track and signals work, grading, drainage, and utility relocations in the Town of Halton Hills (Acton) in support of Kitchener GO service extension. | Apr-24 | TBD | | | 2026Q2 (new date) |
| GO Expansion | KI | Georgetown GO Station Improvements & Layover (Phase 1): Construction of a new island platform, bus loop, passenger pick-up and drop-off area, and a pedestrian bridge. | TBD | TBD | | | 2027Q4 (new date) |
| GO Expansion | KI | Georgetown GO Station Improvements & Layover (Phase 2): Extension of the pedestrian bridge from the island platform to the North parking lot, removal of layover tracks and rehabilitation of the parking lots. | TBD | TBD | | | 2027Q4 (new date) |
| GO Expansion | KI | Kitchener Line Extension | Guelph Subdivision Package 3: Bridge reconstruction, grading and drainage for passing track extension, track and signals works, retaining walls, and trenchless twin culverts. | TBD | TBD | | | Project Removed |
| GO Expansion | Toronto | Technical Services for both task based and highly skilled individuals. | | | | | 2026Q2 (new entry) |
| GO Expansion | Toronto | Program Oversight (Auditing, Analysis, Assurance) for non-conflicted entities, performing audit and oversight functions. | | | | | 2026Q2 (new entry) |
| GO Expansion | Toronto | CMS - Commercial Management System. | | | | | 2026Q2 (new entry) |