    Toronto Toronto | KING Toronto | 57.6m | 16s | Allied | Bjarke Ingels Group

    With cladding activities having resumed on January 13, much progress has been made. Over the seven work days since then (no activity on Thursday, January 15th due to the storm), the Level 5 cladding has been completed over the entire south facade, as well as the short east facade segment...
  2. A

    Toronto Toronto | KING Toronto | 57.6m | 16s | Allied | Bjarke Ingels Group

    No visible activity at King Toronto today, but yesterday was another good day for the cladding crew. Both tower cranes were active during the day. A number of additional Level 5 cladding and glazing sections were installed along the south facade. The amount of work done in just two days...
  3. A

    Toronto Toronto | The Taylor | 121m | 36s | Tricon | Diamond Schmitt

    Permits for conversion of the office space planned for the 2nd, 3rd, and 4th floors to residential were applied for in August 2025. My understanding, from on site staff, is that the new units are to be operated as part of the overall residential rental building, and not as a hotel. Meanwhile...
  4. A

    Toronto Toronto | KING Toronto | 57.6m | 16s | Allied | Bjarke Ingels Group

    Reversal of Fortune As of yesterday, Monday January 12 - there had been no visible cladding activity since December 22 - starting to wonder if the project was being hit with another delay like the previous December / January timeframe - and then the cladding crew showed up today, and they have...
  5. A

    Toronto Toronto | KING Toronto | 57.6m | 16s | Allied | Bjarke Ingels Group

    The Level 5 cladding has been completed on the entire west facade, and has started on the south facade, moving eastwards from the south-west corner of the building. West facade: South Facade:
  6. A

    Toronto Toronto | The Park Retirement Residence | 54.6m | 15s | Verve | Giannone Petricone

    The entire 462 Wellington West parking lot has now been closed off and Verve's Park Retirement Residence appears about to start construction. Building permit for structural work within the heritage building to support the new facility was been issued on November 3 while the Mechanical...
  7. A

    Toronto Toronto | Natasha Residences | 156.9m | 47s | Lanterra | BDP Quadrangle

    A couple of photos from the south side of Natasha - work has definitely restarted, with interior demolition activities back underway. Contractor pickups on site, with openings on the south side for debris exiting the building.
  8. A

    Toronto Toronto | KING Toronto | 57.6m | 16s | Allied | Bjarke Ingels Group

    Thursday morning, December 18: Level 5 cladding installation activities have reached the corner of the King Street facade and the west facade over the driveway. Much of the cladding along King Street is obscured by the hoarding for the legacy building facade restoration activities. With what...
  9. A

    Oakville Toronto | 157 Cross Avenue | 203.5m | 61s | Distrikt Group | Teeple Architects

    A historical anecdote. Around 25 or so years ago, a relative worked at the optician shop in a small strip mall on the north side of Cross Street from the Oakville GO station. She lost her job when the store closed - due to redevelopment of the site - right across from the GO station - to...
  10. A

    Toronto Toronto | Portland Commons | 71.7m | 15s | Carttera | Sweeny &Co

    December 5th - Sunrise Over Portland Commons:
  11. A

    Toronto Toronto | Portland Commons | 71.7m | 15s | Carttera | Sweeny &Co

    First signs of occupancy at Portland Commons - Christmas Party at the top floor of the Portland Commons north portion of the building. Presumably the tenant to be occupying the area, using this as both an appropriate locale for their Christmas Party and to introduce the staff to their new home.
  12. A

    Toronto Toronto | KING Toronto | 57.6m | 16s | Allied | Bjarke Ingels Group

    Tuesday, November 25 - Level 5 cladding activities have now reached King Toronto's outside walls. A couple of late afternoon photos of Level 5 cladding installation activities on the east end of the King Street facade:
  13. A

    Toronto Toronto | KING Toronto | 57.6m | 16s | Allied | Bjarke Ingels Group

    Thursday morning, November 6. Much activity today. Both tower cranes are operating this morning. Work started recently on the ground level of the north-east corner heritage building, presumably part of customer requirements / specifications for tenant occupancy of the retail areas. At least...
  14. A

    Toronto Toronto | KING Toronto | 57.6m | 16s | Allied | Bjarke Ingels Group

    November 3 - Monday end of day. Major progress in the Level 4 cladding installation today - may be the best single day yet for King Toronto, in spite of the midday weather hold as the storm cell passed through. First, a couple of photos from Friday afternoon (not previously posted - and one of...
  15. A

    Toronto Toronto | 160 Front West | 239.87m | 46s | Cadillac Fairview | AS + GG

    Some Golden Hour images from last night: