carturo15
Active Member
Hi Everyone! When do you think this building will be ready for owners? Last time I checked Aug. 2012 was the date. The building is 3 levels below grade and 13 stories above. Remember it's a gold LEED building, so green roofs, rain water collection, etc.
I am guessing the will be moving the 3rd floor in around March 2013. Thoughts?
With the winter coming up, contruction gets very complicated for the underground. They should be on the ground probably by April, then maybe 3 months more doing the first and second floor, that is July and then 4 or 5 months for the remaining 11 floors, that brings us to December 2012 for the concrete structure and finally 10 months doing the interior. I am guessing occupancy will start around October 2013