Notwithstanding the date in the last letter, according to the Tarion rules for critical dates, within 30 days of the completion of the roof slab, a new final tentative date or firm occupancy date must be set.
How can you confirm the milestone of the roof slab being completed has been met? This milestone should supersede the date provided in the last letter. As I recall there is an extra paragraph noting the completion of the "roof assembly"
Very interesting! I learn something new everyday. Why don't you give them a call and ask?