Nov. 24 - Down to P4 now

92427
 
I don't think they will have finished with drilling piles and concrete placement, but it looks pretty good that they will have completed a fair number of them.
 
Must be fairly deep now. Pile driver on site now.

download.png
 

Attachments

  • download.png
    download.png
    858.4 KB · Views: 505
B.3. 18:35 Ice District BG (Tower and Podium)
Dialog - Darrell Halliwell and David James

Motion of support with conditions:
1. Extend paving materials used adjacent to the residential tower throughout the laneway to enhance the pedestrian and cyclist experience.
2. Provide sufficient lighting along the extent of the laneway facade to create a safe and welcoming pedestrian and cyclist experience.

https://www.edmonton.ca/city_government/documents/EDCMinutesNovember15.pdf
 
PERMIT_DATE December 09, 2016
PERMIT_NUMBER 162139487-046
JOB_CATEGORY Commercial Structural Framing
ADDRESS 10324 - 103 STREET NW
NEIGHBOURHOOD DOWNTOWN
JOB_DESCRIPTION To construct a STRUCTURAL FRAME ONLY for a 4-storey underground parkade (Ph 2) addition to Ph 1 Frame Only (see-030) and complete construction of Ph 1 (mechanical and electrical installations) "ICE district parkade"
BUILDING_TYPE Engineering (490)
WORK_TYPE (05) Structure
ZONINGAED, AED, HA
 
I suspect this will have multiple cranes, then, as that is pretty far south for the tower.
 