Had a good look at the site this morning as I was waiting for the light to change. Removing the 2 buildings that site still looks pretty small for the size of building in the renderings. However it will make quite the impact as you come down the hill. Will try to get a good shot from the NE and NW corners. but that intersection is a bit busy right now, the sound wall is being replaced and there is a lot of truck movement.
 
Construction of a new 8 story multi-family rental development in St. Albert, on the former site of the Flying Pig Pub. The development will be Canada's first 0 emission multi-family development.

Project will begin construction in summer 2020, with completion 18 months later.
Municipality: St. Albert
Sector: Residential
Type: Apartment: Low-Rise
Schedule: 2020 - 2022
Estimated Cost: N/A
Stage: Under Construction
Developer: Niche Developments

 
Last edited:
Pig in a blanket
IMG_6664.jpg
 
Finally a larger rendering:

1611768916632.png

1611768916632.png1611774253456.png1611775893816.png

The concrete and steel structure will have a commercial main floor with 7 storeys of residential above. Geoexchange technology will eliminate dependence on fossil fuels for heating, cooling and air circulation. An integrated solar panel energy system will offset common area and tenant utility costs, and will make this St. Albert's first zero energy building.

A landscaped courtyard at the second level is an amenity available to all residents, and most will have views of the Sturgeon River and river valley.

Suite sizes are a mix of studio, one- and two-bedroom, with approximately 17 suites per floor and a total of 119 residential units. The development is situated in downtown St. Albert in the Braeside neighbourhood, offering access to walkable and green spaces, the Sturgeon River, and all the benefits of the city's core.
 