From Ducey on SSP:
They are charging ahead on the Station Lands/ Epcor part 2 tower. They are excavating to the east of Epcor and have broken thru on the roof of the parkade where the new tower will go.

I could post some pictures but cant find a way to do so.

Our own @Airboy also said on SSP:

A very large Concrete pump was on site this morning as well.
 
From Ducey on SSP:
They are charging ahead on the Station Lands/ Epcor part 2 tower. They are excavating to the east of Epcor and have broken thru on the roof of the parkade where the new tower will go.

I could post some pictures but cant find a way to do so.

Our own @Airboy also said on SSP:

A very large Concrete pump was on site this morning as well.
Pump is still there:

D544AE28-548F-471A-9A8B-399D27E0518F.jpeg
 
Pagnotta Inc.
4,516 followers
3m • 3 minutes ago

Station Lands Update! As of May 30th we have completed the raft slab pour inside the existing EPCOR parkade on level P4! We have poured 2/3 raft slabs to date, for a total pour volume of 324.5 M3. Big thanks to @ledcorgroup for having us involved in this project.