Ol' timey wooden power polls be gone!
This will be good to see completed. One question though, is there going to be more construction next year further west of the current section being finished? Personally I think I would be happy with a simple continuation of this design to proceed all the way to 124th Street.
We already got the worst segment out of the way too with this year since Jasper Ave -> Vic Park Rd via 116th is a big connector for in/out of downtown.Year 1 (2025) - 114 Street to 117 Street
Year 2 (2026) - 117 Street to 121 Street
Year 3 (2027) - 121 Street to 124 Street
Next year is the largest in terms of amount of construction.
We already got the worst segment out of the way too with this year since Jasper Ave -> Vic Park Rd via 116th is a big connector for in/out of downtown.
Is it the same contractor for the two other spreads?
The next two years will also provide Jasper Ave with it's most visually appealing and pedestrian friendly infrastructure - that being continuous raised crosswalks on both the north and south sides of the street (except for 121St).
View attachment 693453
In terms of contractor, I'm guessing the same one was secured for the full three years - would mean a lot more work and cost to go through the bid/selection process every year and I imagine a better price can be secured by putting all three years into contract.