What: To prepare for the construction of the new Event Centre, preliminary works will include installation of fencing, mobilization of site trailers and equipment within the construction area, topsoil removal, implementation of a hauling road behind the South Side Stands, and modifications to TD Place to maintain operations during the redevelopment.
Why: Preliminary works will support the construction of the new Event Centre, east of the east endzone, within the Great Lawn.
When: Preparatory activities for Event Centre construction will begin in early December. Further information on project timelines can be found on the project website.
Where: The limits of construction associated with this project are within the Great Lawn. As work begins, fencing and hoarding will safely separate construction zones from public areas to minimize disruption and ensure a safe environment for everyone.
Who: The City of Ottawa has retained the contractor, EBC Inc., to complete the work.