From the RBC
website:
February 2008
Construction continues on schedule. The self-climbing core forming system, for the Tower elevator core, and pouring of the concrete for these walls, will continue upwards ahead of the concrete floor slabs. Concrete slabs will be poured for floor levels 15, 16, and 17 in the tower area. Curtainwall installation in the tower will be completed on levels 8, 9, 10 and 11. Elevator installation will continue in the high rise bank and service elevators. Preparation will start for installation of the floating floor system on the 11th floor mechanical rooms. Forming and pouring of the second floor slab in the north podium area will continue.