Re: udpates on CTV and Jack Astor's?
here's an update from the PCL site....looks like the Yonge St. hoarding will be coming down very soon....
As of March 22/07):
General Comment:
Currently setup with PCL Phase 8 (one way on Victoria Street, effective November 10, 2006).
Yonge St. hoarding removal to start April 16, 2007.
Dundas St. hoarding removal to start June 3, 2007.
Below Grade:
All below grade escalators (12, 13, 22, 23, 26, and 27) commissioned and ready for TSSA inspections.
No progress to TTC ceiling at B1.
No work along KK wall/shaft (awaiting duct enclosure CO).
Security roughin started (CO for PS9’s required to complete).
Above Grade:
Commissioning of escalators 1, 2, 3 and 4 to be complete this week and ready for TSSA approval by next week.
Glazing on Yonge/Dundas St. L1 (storefronts) and backpans in progress nose Curtainwall.
L4 tie in glazing to ‘nose’ in progress.
Stair #6 and 7 framing/glazing in progress (Stair #4 and 5 complete).
Siding along south half of Victoria St. complete this week. Klimber to relocate to north half of Victoria St. next week (1st 3 bays complete next week).
Siding along Victoria St. and Gould St. to be complete by end of March 2007.
Complete balance of L6 raised slabs and L4 seating next week.
Stair # 4, 5, 6 and 7 are poured.
Firespray continuing at L7 and Scheduled to complete all but theatres at North by end of April.
Roofing cap sheet in progress on main east roof. L4 terrace along Dundas to start next week.
Elevators SE1/SE2 scheduled to be complete by the end of March/ early April. TSSA to inspect SE1 March 26, 2007 and SE2 April 9, 2007.
AMC theatres are continuing with scaffold and firespray (1, 2, 3 and 11, 12, 13) .
AMC ceiling framing in common area L4 in progress.
Ground floor CRU walls currently being framed and drywalled will continue over the next two weeks.
O’Keefe lane duct work near completion; storm/diesel line work to start tomorrow and follow with landscaping.
Loading dock waterproofing in progress – pour slab next week.
Base building drywall continuing L10 to L4 – washrooms L10 – L8 roughin in progress and electrical rooms being roughed-in with panels.