Update from the PCL Website, from a couple of weeks ago.....looks like the hoarding on Dundas will start to come down effective Jun 3.....
As of April/07):
· Yonge St. hoarding removal 80% complete
· Dundas St. hoarding removal to start June 3, 2007
· Hoist removed April 30, 2007
· Elevator SE1 in operation
· Power on late April 2007:
· All below grade escalators commissioned and ready for TSSA inspections
· Security rough-in ongoing - door/frame/hardware continuing
· Commissioning of escalators 1, 2, and 4 complete. Escalator 3 in the process of commissioning
· Glazing on Yonge/Dundas St. L1 (storefronts) and back pans and seals in progress
· Stair #6 complete and stair # 7 glazing is in progress
· Siding continuing along Victoria St.
· All main concrete pours complete
· Firespray on-going to theatres/AMC areas
· Roofing cap on-going - main roofs complete
· AMC L4 ceiling framing and GWB in progress
· AMC theatres progressing with studs, GWB, and M&E rough-in
· Ground floor/L2 CRUs continuing to board and complete work
· O’Keefe landscaping in progress
· Doors, frames and hardware continuing
· Base building walls /shaft is starting