A link to Renx.ca about this project - https://renx.ca/bouwinvest-canada-woodbourne-first-capital-development-toronto. Info on new partnership owner and imminent start of rest of demolition and expected start of build.

Relevant bits and bobs from the above:

1682000336852.png


***

On demolition we just get 'soon' for a timeline for the remaining buildings

***

On retail we get this:

1682000540764.png


On sustainability we get this:

1682000637584.png


^^^ sounds like an ongoing partnership with a pipeline to me.

***

Indeed on the above, though Bouwinvest appears to be be looking at other partnerships as well, with a particular eye to purpose-built rental:

1682000749311.png
 
Can excavation proceed before shoring, or is this preparation for levelling before shoring?

They do not have either shoring or foundation permits issued as yet. They don't have have the drain/site-service permit yet.

And this doesn't look any of these to me.

It looks like clean up (removing old foundations that might be in the way of future work, and then backfilling to set up for shoring.)
 