January 2018 Construction Update
Since our last update, the concrete pour for the Alter community has been completed. Window installations are taking place on the 30th floor along with rough-in plumbing and electrical work. Interior finishes such as drywall is being installed on the 25th floor, paint is on the 21st floor, tile installations on the 18th, kitchens on the 17th, and flooring is now on the 12th floor. The mechanical penthouse walls are almost complete. Once done, this allows the site to begin working on the mechanical systems for the community, moving ever closer to the start of occupancies.