Westside story: The core went up another level and the crane jumped three sections and a third tripod support was added to crane# 2. An additional steel floor was added so it's all very uplifting for the joyous holiday season

IMG_1419.jpeg


The lower half of the core

IMG_1420.jpeg


Eastside Story: overall photo

IMG_1421.jpeg


A closer look at the southern half of the level 02 forming and rebar ready for its marathon Saturday pour. In the upper right section near crane#3, there are two workers using compressed air to flush out any debris that could end up leaving an unwanted impression in the ceiling of level 01. Wouldn't want to see a used pizza box stuck in the ceiling above a parked bus :rolleyes:

IMG_1422.jpeg


Trackside: There was a yellow rectangular steel construction that sat at the southern end of the elevated park. I thought it was to be a platform for a crane that was to be placed on this part of the elevated park, but it was removed last night.