• Thread starter Suicidal Gingerbread Man
  • Start date
December 28 - looks like the core has been reduced for the first time on this jump.

KvUgL3.jpg
 
Mild Friday

Westside Story:

Some panels were removed from the top section of the core and stored down on level 02 of the bus depot. The north section of the core is rising at the time this was posted. The pour happened last Saturday. It has taken 6 days for the core to begin rising. Usually, they raise the platforms the day after the pour. Also, the pour was only about 10 or 11 hours instead of the normal 14 to 15 hours

IMG_1458.jpeg


A closer look shows the inside of the forms that have yet to be removed in this southern section of the core. It will be interesting to see what this looks like once they've re-adjusted the top platform

IMG_1459.jpeg


Eastside Story:

You may notice the yellow and blue forms that came from the top of the core a few days, ago resting on the deck of level 02. You may also notice that the concrete pumpers on either side of the crane#3 have had extensions added to increase their height. Other work is happening along the east wall next to 18 Yonge St. and the north wall at trackside as well as the addition of a few more concrete columns,

IMG_1460.jpeg
 
All right for some, a three day work week, Friday

Westside Story:

Short week but lots of activity within the core and installation of the corrugated metal decking, distinguishing the floors, one from the other.

IMG_1466.jpeg


A closer look at the top of the core, reveals deconstruction of the formwork to reduce the north/south footprint of the core

IMG_1463.jpeg


Another view of the corrugated metal deck being installed, and spot welded, to the supporting steel beams

IMG_1465.jpeg


A lot of the deconstructed formwork from the reduced core has been stored on the floor, of level 02 of the bus terminal. It's being stacked in multiple piles and you may notice, the blue coloured, steel superstructure of what was the work area on the top of this section on the core.

IMG_1464.jpeg


Eastside Story:

A general picture of the area show additional forming continuing along the crash wall to the north, parallel to the train tracks,

IMG_1467.jpeg


A closer, and unfortunately darker photo, showing the rebar work in progress along the 18 Yonge St west facing wall and some more detail of the two up/down ramps for the bus depot

IMG_1468.jpeg
 
All right for some, a three day work week, Friday

Westside Story:

Short week but lots of activity within the core and installation of the corrugated metal decking, distinguishing the floors, one from the other.

View attachment 169726

A closer look at the top of the core, reveals deconstruction of the formwork to reduce the north/south footprint of the core

View attachment 169733

Another view of the corrugated metal deck being installed, and spot welded, to the supporting steel beams

View attachment 169735

A lot of the deconstructed formwork from the reduced core has been stored on the floor, of level 02 of the bus terminal. It's being stacked in multiple piles and you may notice, the blue coloured, steel superstructure of what was the work area on the top of this section on the core.

View attachment 169734

Eastside Story:

A general picture of the area show additional forming continuing along the crash wall to the north, parallel to the train tracks,

View attachment 169736

A closer, and unfortunately darker photo, showing the rebar work in progress along the 18 Yonge St west facing wall and some more detail of the two up/down ramps for the bus depot

View attachment 169748
The latest @Michael62 update stitched. Tried to use content aware mode to fill in the gaps, then added a 5-pixel gaussian blur to minimize the damage.
TL;DR = I tried
Untitled_Panorama2.jpg
 
^ Thanks. Guess they'll have to move that win-loss-tie public art hanging from the ceiling of that open area?
 

Back
Top