EastYorkTTCFan
Senior Member
Actually I would say that Eglinton west is more critical as the yard and matanice facility are all in the West end of the city.I don't know if they have or haven't BUT a contractor wanting to make a profit will delay as much as possible while still reaching the deadline to minimize carrying costs on labour. They'll start with the deadline and work backward to determine the latest time when work on a section needs to be started. Of course, if labour is available and has nothing else to do then you put them to work.
I think Yonge is the critical path.