JasonParis
Moderator
Why don't we just build full crossovers at every station to allow for maximum flexibility? It's cost, right?
|
|
|
I presume this is an attempt to take a bite out of Verster's statement that Yonge station must be completed on the pre-covid schedule or pay penalties.
Vendors considering a bid on Ontario Line and GO Expansion will be watching this pretty closely. I'm guessing in Alliance style tenders that change of law impacting cost will be a risk Metrolinx is forced to absorb.
I presume this is an attempt to take a bite out of Verster's statement that Yonge station must be completed on the pre-covid schedule or pay penalties.
ML really doesn't know what they're doing is one of the biggest risk. They keep changing their minds.Last we heard, IO and MX were having a lot of trouble with P3 procurement, particularly around GO Expansion, because the private sector was not willing to take on the level of risk that IO/MX desired to load onto them.
It's not like they had much to begin with. The Presto mess tells it all.All large contracts have a claims process where the contractor asks for relief from things that went amiss, invoices for scope changes, and cost of mitigating extraordinary unforeseens, etc. Normally that happens quietly and even if there are disputes, they get arbitrated in private.
What gets a little silly is when the contract is so rigid and the in service date has such political ramification that the parties have to wrangle these things out in public with little room to compromise.
ML lost a lot of credibility when it took Bombardier to court alleging non-performance on LRT production, when ML’s real objective was to downsize its order. Now we have ML saying it will enforce the Crosstown contract to the letter.
Nobody really expects a project this big to come in on the exact promise date. I have not heard of any single large booboo by the contractor, and the known glitches (eg the discovery work at Yonge-Eglinton) are definitely unforeseens. ML ought to accept some of that risk.
All I can say is, be careful what you ask for. We want the P3 vendors to have good engineering departments, not good legal departments.
- Paul
Welcome Yes, this the Eglinton Crosstown thread.is this the eglinton light rail chat?
Why don't we just build full crossovers at every station to allow for maximum flexibility? It's cost, right?
CTS now suggests the COVID-19 pandemic is hurting their production. However, CTS’s lack of productivity was a problem from well before the pandemic hit. CTS has achieved their monthly production rates in only four months out of the last 26 months. Since August 2018, CTS has achieved only 72% of their planned volume of work.
We want the P3 vendors to have good engineering departments, not good legal departments.
We always sayThis statement is truly brilliant.
As a vendor - if you need a good legal department then you are already in trouble. Or, you are the trouble.
That may be true for the TTC's streetcar network switches due to some unique aspects to the surface network and that they are embedded, but that is not true for the majority of rail switches. A non-embedded switch, that uses standard profile rail, that is in "normal" position can be traversed at full line speed. Only when the switch is in "reverse" position is there a need to reduce speed. In the UK, for example, High Speed 1 has track switches that are traversed at 225-300 km/h when set in the "normal" or straight through position.Generally speaking trains need to go slower through switches. Having less switches allows a faster overall speed.
Since we don't know the reason for the delay is cause by Crosslinx unable to build the project on time or ML keep changing their plans making it very difficult to stay on time, we can't just conclude one party is at fault.Metrolinx CEO addresses litigation initiated by Crosslinx Transit Solutions regarding Eglinton Crosstown LRT project
Metrolinx CEO addresses litigation initiated by Crosslinx Transit Solutions regarding Eglinton Crosstown LRT projectblog.metrolinx.com
Yikes, theres no way this lawsuit holds up in court right? If CTS claims the governments refusal to declare an "emergency" for contract terms hurts their work progress, Metrolinx can just say you guys never completed your tasks on time. Covid did nothing to hurt you