toronto647
Active Member
lol more likely an update for an update for an another prior updateThis is absurd. We're now waiting for an update for an update.
|
|
|
lol more likely an update for an update for an another prior updateThis is absurd. We're now waiting for an update for an update.
SSE is opening 2030 ish optimistically... so by your count we are another 6+ years to go for the Eglinton LRT openingHonestly, I do not expect this to open before the Scarborough Subway.
SSE is opening 2030 ish optimistically... so by your count we are another 6+ years to go for the Eglinton LRT opening
Where are you getting the 20% from? I only see 89.1%, 66.4%, and 6.3% in the "testing and commissioning" work stream.tbh, he should have said that the training/commissioning phase is scheduled to take 6 months (assuming nothing goes wrong), and according to the dashboard, we are at least 20% of the way through.
View attachment 509578
Almost nothing made public includes operational costs, it's kind of stupid.To be fair, I hate that all these projects include the 30 year price tag. Inflation screws up past project numbers and those didn’t even include the lifetime costs. So people will say like we built the subway line for eight dollars in 1950
An example from London from Crossrail - the communication was "2022", then "first half of 2022", and then the opening date was announced.Nice summary by voilan above. My general take for what its worth.
Mr Verster was being a little too defensive initially but he softened up towards the end. I think that the project is close but anytime there is a software issue, there could be alarm bells going off on timelines. The physical side of the project has been largely overcome if not completed (other than surface works) which is a technicality for this project.
If the software is successfully rectified, I can see this moving quite quickly. Certainly not beyond 2024.
Still infuriating that he refused to commit to even an estimate. Could have easily set expectations appropriately IMO.
Agreed - the testing and commissioning of a brand new line takes a while, and as Ottawa has showed - you don't want to rush / half arse it.I'm just speculating, but it sounds like something similar to my understanding of the situation with the Confederation Line in Ottawa, where there are serious issues preventing the normal operation of the line that they're struggling to correct and that will potentially require a large investment of time and money to fix.
Summarizing:
- Verster:
- They now have an internal schedule for all project elements, but will not announce a date as a result of recurring issues encountered during testing & commissioning
- Commit to progress updates every two months
- Technical update given on testing & commissioning problems thus far:
- Issues with signaling requiring software updates, which require tests of their own
- Widely discussed track issues
- Groundwater penetration of stations and tunnels
- Sloane stop repairs
- Generally vague, but clear that process is not near completion
- Remaining construction:
- 400m of surface remaining to complete
- Yonge and Eglinton is primary focus of remaining construction (watermains, road resurfacing)
- "The stations look to be complete" barring testing and commissioning
- Station occupancy permits:
- Received for most surface stops
- Other minor updates
- Q&A:
- Verster refuses to give a date due to lack of progress (mentions fleet and signaling issues), commits to giving a date upon completion of testing & commissioning phase and updates every two months (including quantitative updates on testing & commissioning)
- Recent ruling that CTS litigation in May will be addressed through arbitration
- Re-emphasizes that Metrolinx has an approximate date internally, but defects/issues mean lack of confidence in any date given to the public
- Presumably this is an indication that "no credible plan" is no longer the Metrolinx position.
- Couple of confrontational questions, Verster responds that he's accountable to Ministry and that new bimonthly presentations are a step up in transparency
- Total budget (previously reported): $12 billion, currently at $12.56 billion
- On Finch: Significant progress made, but all projects have been impacted by COVID (touts progress on various other projects)
- "We're not that far away" on ECT, but ML must be confident on date before announcing
- Testing & commissioning dashboard will be updated every two months, but not in real-time
- ML and collaborators are committed to delivering projects as soon as possible
- 1400 defects and deficiencies have been addressed, but new ones are discovered over time (general error, technical issues, miscommunications).
- ML must be meticulous in "getting it right"
- Do not draw conclusions from "every two months" (i.e. extrapolating out to much longer delay)
- Commits that ECT will open "flawlessly" (EDIT: journalist asked whether Verster would stake his reputation upon it, Verster responds affirmatively)
- Groundwater issues specifically mentioned at Keelesdale
Speaking of, do the truck issues in Ottawa affect finch west?Would love to know what exactly is meant by fleet availability issues. The cars are brand new!!
Ah, you have safely time travelled into the future, I see.When it does finally open Torontonians will be blessed with the slowest, lowest capacity, highest operation cost, most unreliable, and most disruptive mass transit rail system possible.
Yes as well Mississauga since they are the same carsSpeaking of, do the truck issues in Ottawa affect finch west?
Hold on a second here.Yes as well Mississauga since they are the same cars