News   GLOBAL  |  Apr 02, 2020
 10K     0 
News   GLOBAL  |  Apr 01, 2020
 42K     0 
News   GLOBAL  |  Apr 01, 2020
 6.1K     0 

With construction complete, why would the lawsuit delay operation? That's not been a factor on Line 5.

Not would delaying operation be in either parties interest.
note that the crosstown guys also sued the ttc for the same exact reason back in May 2023
It quietly went away
 
Have the past Crosstown legal issues gone away? It took years after TYSSE to be dealt with, didn't it.

Heck, TTC still has TYSSE as an open project.
 
Have the past Crosstown legal issues gone away? It took years after TYSSE to be dealt with, didn't it.

Heck, TTC still has TYSSE as an open project.
"gone away" as in never to be brought up again? definitely not. The whole contract was supposed to be structured so that legal issues dont happen until after project completion
 
With construction complete, why would the lawsuit delay operation? That's not been a factor on Line 5.

Not would delaying operation be in either parties interest.
Not necessarily the same from my understanding of it.

Finch West lawsuit is tied directly to an operation dispute with Mosaic claiming they are supposed to be operating the Finch West line, not the TTC. So if it's tied to an operational issue, it would most certainly impact when the line could begin operations. Of course Metrolinx could just ignore it, which wouldnt help their fight in court (unless the issue is settled out of court).


Eglinton had a couple lawsuits, the latest was Crosslinx was claiming that the TTC was making numerous requests and inputs that go above and beyond their contractual responsibilities and it was causing the project timelines/costs to be affected. They were claiming that Metrolinx was not doing their "job" in reigning in the TTC and that was a breach of contract.
 
Finch West lawsuit is tied directly to an operation dispute with Mosaic claiming they are supposed to be operating the Finch West line, not the TTC.
I believe you are wrong about that. The link doesn't mention anything about Mosaic operating the line.

From the article, it looks like the issue is about details in the operational agreement with TTC, which Mosaic wasn't involved in. I don't know what those are, but it almost sounds like there are areas where neither TTC nor Mosaic appear to be responsible for - but that's speculation.

Eglinton had a couple lawsuits, the latest was Crosslinx was claiming that the TTC was making numerous requests and inputs that go above and beyond their contractual responsibilities and it was causing the project timelines/costs to be affected. They were claiming that Metrolinx was not doing their "job" in reigning in the TTC and that was a breach of contract.
A lot more than a couple. I tried to find information on a particular one once, and I couldn't find it, because there were dozens if not hundreds of cases that Crosslinx was involved in.
 
All jokes aside, it really is amazing to me that none of the Canadian news organizations have uncovered what the delay is really about.

It's not a matter of national security. Nor are news orgs bound by legalities until something is before the courts.

Why have none of the news outlets come up with anything?

This feels like exactly the kind of thing Toronto Life or Macleans would do a big cover story on.

There are lots of people out there who know what it's delayed. No one will leak it?
 
Last edited:
I believe you are wrong about that. The link doesn't mention anything about Mosaic operating the line.

From the article, it looks like the issue is about details in the operational agreement with TTC, which Mosaic wasn't involved in. I don't know what those are, but it almost sounds like there are areas where neither TTC nor Mosaic appear to be responsible for - but that's speculation.
Part of the dispute (not the entire dispute) involves the TTC operating the line:

A legal challenge, launched in early August by Mosaic Transit Partners, claims Metrolinx “breached its contractual obligations” by entering into a separate operator contract with the TTC to run the line which, the consortium believes, is “inconsistent” with the original construction agreement signed with the province.



The core of the dispute:

At the heart of the dispute: the relationship between Mosaic, Metrolinx and the involvement of the TTC.

The lawsuit argues that when Metrolinx entered into a contract with the TTC to operate the Finch West LRT when it opens, it excluded the builders from those conversations. As a result, Mosaic argues, the TTC has been failing to fulfill key tasks that the operator has to undertake before the line can be complete — with no accountability measures in place

The agreement reached with the TTC, the lawsuit alleges, is “grossly deficient and inconsistent,” with the original contract Mosaic signed, and “imposes virtually no obligations upon the TTC.”
 
Part of the dispute (not the entire dispute) involves the TTC operating the line:

A legal challenge, launched in early August by Mosaic Transit Partners, claims Metrolinx “breached its contractual obligations” by entering into a separate operator contract with the TTC to run the line which, the consortium believes, is “inconsistent” with the original construction agreement signed with the province.



The core of the dispute:

At the heart of the dispute: the relationship between Mosaic, Metrolinx and the involvement of the TTC.

The lawsuit argues that when Metrolinx entered into a contract with the TTC to operate the Finch West LRT when it opens, it excluded the builders from those conversations. As a result, Mosaic argues, the TTC has been failing to fulfill key tasks that the operator has to undertake before the line can be complete — with no accountability measures in place

The agreement reached with the TTC, the lawsuit alleges, is “grossly deficient and inconsistent,” with the original contract Mosaic signed, and “imposes virtually no obligations upon the TTC.”
The issue is the interrelationship between the TTC and Mosaic, once operations start (presumably in demo mode - aka test running).

Reading between the lines, I get the impression that (as with the case with Crosslinx) that Mosaic wasn't expecting to have to deal with TTC inspecting everything to their own standards. and applying their safety requirements.

I assume that Metrolinx's competency (or lack of it) in legal contracting will once again be their undoing with these cases.
 
All jokes aside, it really is amazing to me that none of the Canadian news organizations have uncovered what the delay is really about.

It's not a matter of national security. Nor are news orgs bound by legalities until something is before the courts.

Why have none of the news outlets come up with anything?

This feels like exactly the kind of thing Toronto Life or Macleans would do a big cover story on.

There are lots of people out there who know what it's delayed. No one will leak it?
Maybe this is minor, but there are some really mundane things. Systems integrations tests proceeded a lot slower than scheduled because of inefficient scheduling, etc.
 
Work has started on the existing unpaid fare hallway at Kennedy station. I was at it this afternoon and it's been blocked off with signs saying that they are working on it for the crosstown line

54091595656_564c8714ba_w_d.jpg
54091843098_6914aeffb1_w_d.jpg
 
Last edited:
wait theyre only starting NOW?? like 4 months after they were supposed to open????!!!! :mad:
I'm not sure of the exact nature of this work but I'm assuming they're just reconfiguring the farepaid areas. That's something they have a lot of recent experience with from the gate changeover and they likely have a lot of confidence in knowing what challenges could arise and therefore don't think it should take long. Also, if the new configuration is harder to navigate for customers accessing line 2, it's better to have waited so they wouldn't be inconvenienced through more of the project.
 
The issue is the interrelationship between the TTC and Mosaic, once operations start (presumably in demo mode - aka test running).

Reading between the lines, I get the impression that (as with the case with Crosslinx) that Mosaic wasn't expecting to have to deal with TTC inspecting everything to their own standards. and applying their safety requirements.

I assume that Metrolinx's competency (or lack of it) in legal contracting will once again be their undoing with these cases.
My best guess as to what happened:

-Agreements were made in principle about construction between Crosslinx and ML, and ML and the TTC, and these agreements don't completely line up
-Over twenty years, scope, personnel and technology have changed, changing the actual requirements
-Mistakes, sloppy construction and manufacturing errors gradually accumulated, and there was no clear quality control process for all aspects of construction (TTC has different safety standards than ML and Crosslinx)
-Any changes require costs, and all three partners are trying to shove responsibility for changes onto the other two (hence all the lawsuits)
-Money for the project has largely run out, so everyone is focused on minimizing further expenses
-People are avoiding this project because involvement taints you with the stink of failure
-Dougie wants the opening of the line to happen close to an election call, and he's aiming for a spring 2025 election, so it'll open then.
 
Last edited:

Back
Top