There is a photo update literally two posts above yours clearly showing a large tower crane standing in the pit
I know about crane; actually, I posted pictures of the crane mounting work. I just wanted to know if they started pouring concrete for foundation or they still trying to fix the underground water leak(s).
They are not yet ready to pour for the foundation at all.
The floor of the excavation has not been leveled; they did pouring concrete around the base of the crane but nowhere else. The ramp to the excavation still occupies at least one third of the site.
They could work on the west side of the site, but there was still some open water on Friday.
Sounds like an excavation nightmare
I just came across a bit of info in this article (a link posted by kristopher): "...the Yonge Sheppard project is currently under construction to be completed by 2016". Was it scheduled to be completed some time in late 2013-early 2014??