I was under the impression that they started pouring the east side later than they did the west end due to the extra time that it took to remove the truck ramp, which took up a large portion of the eastern half of the site.
this will be interesting too as the east tower is over ten stories taller than the west tower.
Same situation with Tridel-Hullmark Centre right across the street,.... the shorter south tower construction is working on the 8th floor now while the north tower is on the 2nd or third floor. The north tower will have office on bottom and residential condo on top and is much taller than the all condo south tower.