Some updates.
May/June will see the Third Virtual Open House
Excavation underway at Port Credit Parking lot to create a site to build the tunnel box that will be push under the rail corridor around the end of the year and will take a few weeks to do it. Once done, work will start on the station as part of the station walls will be built along with the tunnel box..
.
Work is to start this summer that will see Eaglewood Boulevard extended to Oriole Avenue over Mary Fix Creek and the Intersection on Hurontario being signalizes. Once done, the Inglewood Drive bridge over Mary Fix Creek will be remove along with the traffic light intersection. The creek will see new retaining wall which is underway now, as well a new bridge over it for the parking lot.
Construction will take place on the southbound lanes from Sherobee Road to Rathburn. Like the other 2 areas under construction, all will see new road and sidewalk before shifting to the other side.
Grading is taking place on the old Playium site as a staging area for the elevated guideway over the 403 starting in June. The guideway will be made up of precast sections and place using an cantilever bridge.
Not sure when work will take place for work on Hurontario 403 overpass.
Enclosing of the maintenance building well underway. The small building on the north side of the service bay is for washing and getting cars ready for service. All the area east of the complex has been raise as this will be the main entrances off Kennedy Rd for all vehicles with the LRV's using Top Flight to get to Hurontario St
All intersection should be done by June for the construction traffic lights.