The Crest: 7th floor forms visible in the Eastern part
Westernmost tower: 4th floor forms being put in place
Middle tower: 1st floor wall forms being put in place
Easternmost tower: Still pouring P1 wall forms
The Crest is now on 7th floor wall forms at the Eastern part, while the Western part is completing 7th floor pours. The Westernmost tower's 4th floor pours seem to be complete as well
Taken today, July 13th, 2023. The Crest now has 8th floor wall forms visible (Last floor before mechanical penthouse), and the Westernmost of the taller 3 towers has 4th floor walls already poured
Taken today, July 20th, 2023. The Crest is now working on the 9th (Mechanical penthouse) floor, with just the walls and roof of that floor left before it's topped out. The Westernmost of the 3 towers is now on the 5th floor
Taken today, July 28th, 2023. The Crest is now basically topped out, having poured the mechanical penthouse (9th floor) wall forms. The westernmost of the 3 towers now has 5th floor walls poured, with what looks to be 6th floor forms visible
The Crest: Work ongoing on the mechanical penthouse floor
Westernmost tower: 6th floor forms being put in place
Middle tower: Hard to see, but still looks to be on the 1st floor wall forms
Easternmost tower: 1st floor wall forms being poured
Hard to see, but the middle and Easternmost towers now have 2nd floor forms in place, while the Westernmost tower has 7th floor wall forms in place now. The Crest building is still working on the mechanical penthouse
The Crest: Still working on mechanical penthouse, progress from here will be harder to see (E.g. interior, wiring, plumbing, etc.) until cladding starts installation
Westernmost tower: 8th floor wall forms in place
Middle tower: Hard to see, probably on 2nd floor
Easternmost tower: 2nd floor poured in some places
The Westernmost tower is now on the 10th floor, while the middle and Easternmost ones just had a large 2nd floor pour in the remaining part (Where 2nd floor wall forms aren't yet). No cladding on The Crest midrise yet
Taken today, September 15th, 2023. The Westernmost tower is now on the 11th floor, while 3rd floor forms are being put in place for the middle and Easternmost towers
Westernmost tower: 11th floor wall forms being poured (11th floor was just fully poured)
Middle tower: 3rd floor wall forms being put in place
Easternmost tower: 3rd floor wall forms being put in place