cc46
Active Member
Three pics yesterday and today. Trucks in queue at 7 am and a concrete pour 4pm on a Friday.
Just moved in across the street in July and have been taking a picture once every few days. (Trying to from the same spot at least).
Here's a little gif of the progress so far that I've seen.
Thursday Jan 17. A little different from this perspective. The ramp is dwindling.
The first load for phase 2 was just delivered. (north of the wall) ....maybe for phase 3.
View attachment 171539
Haha, looks like a pile of dirt for the ground breaking of the next phase, maybe?What exactly was delivered for phase 2?
The dirt or crushed stone dumped outside the north end of the construction zone is gone. Either they cancelled the ground breaking ceremony and the next two phases or they needed the material for phase 1. I was wondering if another fence push out was in the works?What exactly was delivered for phase 2?