We looked at making QQ westbound only as well eastbound and both were rejected as they didn't support the community. Also, it force the residents to have to spent a lot of time using the Lake Shore to go a few blocks especially when the Lake Shore come stand still. One way not my choice.
I see some of my committee members in the photo and you miss me by 30' to the west.
Had a short talk with Glen and Tory after the event. Both are pushing to have transit to the east build as soon as possible. What took me back was the $900 million that is missing to do it by Tory, considering its been $375m all along.
Glen said the Feb's in the past have said it was up to the P3 boys to fund their 1/3 share of the project. With SmartTrack getting $2B, maybe more money on the way later this year for the east.
99.8% of the work is done. Spadina TTC switches still not working; guardrail on Peter Slip Bridge missing or partly in place; Wooden poles still to be install; some MGT marking still need to be done. Minor detail to be fix and will be completed by July.
Chase 5 cars off the ROW as well TTC drivers telling a few other.
Yes Spadina needs signage to tell drivers to turn left as TTC staff were chasing driver on almost every light. Driver are not aware they can't cross TTC tracks anymore to go east compare to the past is the big issue and was it was expected. Police should have manpower as regular duty officers on various points that are problem sites to deal with it. This was voice by others.
Cycles were flying along the trail as well a few e-bikes.
One big issues is the lack of space between MGT and the ROW for pedestrians to stand while waiting to cross the street. Got caught in one at Bathurst St with 3 cycles waiting to cross where one of the cycles said the same thing.