drum118
Superstar
Sounds like from the sounds of it that there were a few main issues:
1. Toronto Hydro not getting their act together to fund their part in time to start when they were supposed to
2. Unknown Unknowns - all the stuff you don't find out until you start digging
3. Artificial deadline of Pan-Am games (which arguably is necessary due to the location) and probably was part of the bid
Don't think TTC had much to do with the delay, if anything Waterfront Toronto/Pan-Am forced Toronto Hydro to get things done...
I understand the concept of not publicly announcing the $30 million overrun until the agreements were in place (as then they will just not agree to anything but whatever was budgeted). But they definitely should have come out and said there will be significant overruns and we've have a number but aren't releasing it until the agreements are in place...
I guess this is just the first of a list of many items where Ford failed to stop the gravy (just wait for Union and NPS to be complete!)
You are correct.
Hydro 6 months late starting and they had issues during the process that add more cost to their work and this project.
The lake try to reclaim the area that was fill in by flooding various location where underground work had to take place, causing delays as well extra cost to deal with the flooding.
Various changes took place to please the locals that cost more in the end.
TTC play no part in this cost overrun unless it had to do with the 2nd platform that was not part of this project. The 2nd platform delay the opening of the ROW.
The fire department added some extra cost by demanding concrete in place of grass.
Union is well over budget.
Eastern who were the project management help in some of the extra cost by not managing the project like they were supposed to in the first place.
Various trades made changes by upgrading things as it was the correct way to go and added extra costs also.