721irnwrkr
New Member
Your correct the pour has slowed down. The next 3 floors will take 6 weeks each to form and pour because of all the changes going on at these levels,
The cladding will continue to L26, thats one level below the monorail we use which is anchored to L27 columns. Once we have reached L26 our forces
will then go back down to the south/east and south/west and fill in from L3 to L10. This is scheduled to start around July 20th.
The cladding will continue to L26, thats one level below the monorail we use which is anchored to L27 columns. Once we have reached L26 our forces
will then go back down to the south/east and south/west and fill in from L3 to L10. This is scheduled to start around July 20th.