I suppose it is a good thing this was discovered!
Emergency Non-Competitive Contract with Century Group Incorporated for Construction Management Services at the East Wing of Union Station
Origin (November 16, 2020) Report from the Executive Director, Corporate Real Estate Management, and the Chief Procurement Officer, Purchasing and Materials Management
Recommendations The Executive Director, Corporate Real Estate Management, and the Chief Procurement Officer, Purchasing and Materials Management recommend that:
1. City Council receive this report for information.
Summary The purpose of the report is to inform the General Government and Licensing Committee regarding an emergency non-competitive contract that the City has entered into with Century Group Inc. under Purchase Order Number 6051271, to provide emergency structural remediation services at the East Wing of Union Station, in the amount of $2,968,877.09 net of Harmonized Sales Tax ($3,021,129.33 net of Harmonized Sales Tax recoveries).
As a result of the demolition undertaken as part of the Workplace Modernization Program to create office swing space at Union Station, it was discovered that there were significant structural issues with the roof and exterior walls of the fourth floor of the East Wing of Union Station. Once discovered, the structural issues needed to be addressed immediately, as required by the Ontario Building Code, to prevent possible collapse, and to ensure the safety of all personnel on site. The structural issues could not have been found by any due diligence processes prior to construction, as only full demolition exposed the structural issues.
See: https://www.toronto.ca/legdocs/mmis/2020/gl/bgrd/backgroundfile-158541.pdf
The bigger question is how did nobody think of this before..