The Toronto cars were already schedule to be delivered at 3 a month, or higher, until 2019. Much of the Waterloo, Eglinton, Finch, and Sheppard cars were scheduled to be delivered by then (also at about 3 a month), so presumably they thought that they can actually handle 6 a month. Though how much of that depended on the completion of the delayed TR car delivery being finished. They may not have been counting on the recent purchase of an extra 10 TR trainsets.
While the delivery schedule of the TRs has slipped fairly badly up to now, even with the additional 10 trainsets I can't see them slipping so far as to severely impact the production of the Transit City/Flexity Freedom/Metrolinx order. There are 21 TR sets left to be delivered, and provided the get back up to the their previous rate - a set every two to three weeks - they should be fully delivered by the end of next year.