Here's the details on the new (January 30th) streetcar delivery timetable from the
March 23 CRLV Rebuild report. It only sees 40 delivered in 2016, compared to the 63 we'd been promised (the original plus they'd promised the missing 13 from 2015 by mid-year).
Essentially, they are deferring 25 streetcars until 2019. Though my guess is they'll never exceed 40, and at best they will be delivering at least 30 cars in 2020.
View attachment 70058
Also the new
March 23 CEO report gives information on the Flexity failure rate. Essentially 12,000 km compared to the contractual target of 35,000 km. Apparently they have until car 60 to get this right. Though given the glowing reviews that TTC keeps giving the quality of the new cars, presumably this is as-expected, and will improve.
To put this in perspective, the CLRVs are currently 3,870 km and the ALRVs are only 2,091 km.
View attachment 70061