News   GLOBAL  |  Apr 02, 2020
 9.5K     0 
News   GLOBAL  |  Apr 01, 2020
 40K     0 
News   GLOBAL  |  Apr 01, 2020
 5.4K     0 

Screenshot 2024-02-01 at 2.25.18 PM.png
 
Leaving what?

You generally do not tender something very far in advance as price escalation will leave you high and dry. A 30-60 day tender/RFI period, 30 day evaluation and award still provides time to mobilize and start construction for this season.
 
Leaving what?

You generally do not tender something very far in advance as price escalation will leave you high and dry. A 30-60 day tender/RFI period, 30 day evaluation and award still provides time to mobilize and start construction for this season.
But they aren’t awarding a contract they are asking for qualifications. How long does that process take ?
 
I can't imagine once they start this that it will take too long to finish right? Tearing out old parking lots, doing some utilities work, and landscaping shouldn't be too long of a construction period.
 

Back
Top