Updated March 12, 2015
Construction of Stage1 ION, the Region of Waterloo’s light rail transit (LRT) service, is underway in select areas across Kitchener and Waterloo. Read on to find out what’s happening, when and where. Remember that the timing of all work is subject to weather conditions and construction constraints.
UpTown Waterloo, on Caroline
On Caroline, between Allen and Erb, crews continue to install infrastructure needed to relocate third party utility services. In late-March, work to relocate and upgrade the remaining underground utilities, such as watermain and stormwater, will commence.
Detour and way-finding signage alerting drivers, cyclists and pedestrians of the construction area, as well as how they can access businesses is in place will remain throughout construction. In the spring, once the road is ready for the new LRT track, work to build the rest of the ION.
infrastructure (i.e., final curbs, poles and the overhead wires that power the train) will start. Rolling lane closures, rather than road closures, are expected during this phase of construction.
CN railway tracks, from Northfield to King, in Waterloo
In Waterloo, construction to remove vegetation and to build the railway embankment along the CN railway tracks continues, from Northfield to King. Crews are currently working from Columbia towards the Erb and Caroline intersection. The Laurel Trail – from the Erb and Caroline intersection to just before the Laurel Creek pedestrian bridge – will be closed periodically until the end of April. Timing of construction is subject to weather conditions and construction constraints. Detour signs alerting cyclists and pedestrians of the construction area will remain in place.
Also in March, GrandLinq crews will begin to test the soil conditions along the CN railway tracks in the North Parking Lot near Waterloo Town Square. Once testing is complete, crews will begin to clear vegetation and remove pavement along the rail alignment. The North Parking Lot and access to Waterloo Town Square will remain open during construction.
Weather-permitting, starting as early as mid-March, GrandLinq Contractors will begin to build the track and road crossings at Quiet Place, Bearinger, Columbia West, University Ring Road, University and Seagram. During this time, these road crossings will be closed for up to two weeks at a time. More information will be provided in advance of these closures.
Operations, Maintenance and Storage Facility, in Waterloo
Work at the ION Operations, Maintenance and Storage Facility (OMSF) located at 518 Dutton Drive in Waterloo continues. Vegetation has been cleared, the site has been excavated and temporarily graded, a crane has been erected to help pour the concrete foundation for the new facilities and the underground services are now being installed. This facility will be home to the Region’s LRT vehicles and is expected to open in 2016.
King West, Union to Victoria, in Kitchener-Waterloo
Starting as early as March, King, from Union to Wellington, will be closed to through traffic to accommodate the relocation and upgrading of underground utilities, such as watermain and stormwater.
To accommodate construction of the King grade separation, King, from Moore to Victoria, will be closed to all traffic for up to 18 months. This work is scheduled to begin in mid-April.
Access to and from King West at the following intersections will be limited to emergency services, hospital patients, students, local residents and businesses only: Allen, John, Union, Mount Hope, Pine, Green, Andrew, Agnes, Louisa, Wellington, Moore and Victoria South.
Charles, Benton to Borden, in Kitchener
Starting as early as March 23, Charles, from Victoria to Borden, will be closed to through traffic to accommodate the relocation and upgrading of underground services.
GrandLinq will start with sanitary followed by the watermain and storm sewer, starting near Borden and progressing towards Benton.
Access to and from Charles at the following intersections will be limited to emergency services, local residents and businesses only: Eby South, Cedar South, Madison South, Cameron South, Pandora South, Stirling South, Kent, Borden South.
Charles from Benton to Victoria, in Kitchener
Starting as early as March 30, Charles, from Victoria to Benton, will be closed to through traffic to accommodate the relocation and upgrading of underground services.
GrandLinq will start with sanitary followed by watermain and storm sewer, from Gaukel and progressing towards Victoria and Benton.
Access to and from Charles at the following intersections will be limited to emergency services, local residents and businesses only: Victoria South, Francis South, Water South, Gaukel, Ontario South, Queen South, Benton.
Borden, Charles to CN railway tracks, in Kitchener
Work to upgrade and relocate underground utilities on Borden, from Courtland to the CN railway tracks in Kitchener, is expected to begin as early as March 23.
In April, work will continue on Borden, from Charles East to Courtland, to relocate and upgrade the remaining underground services.