If the issues are similar to Crosstown, it's not that the contractor does or doesn't know how to lay to spec.

It's that the spec is unreasonable, and Metrolinx is holding it to an unreasonable tolerance.

You don't need millimeter precision for sidewalks and bike lanes, but that's the tolerance that Metrolinx is holding the contractors to.

Dan
This is what I have heard as well from someone who is quite privy to the discussions happening behind the scenes. Metrolinx is expecting 100% compliance whereas these contractors (and the people they’ve hired from overseas) are used to wiggle room.
 
The article indicates that the track is "out of spec". Is that not the case?
Do you and others have access to the specifications requirements as I don't have them?? If so, please share them so we can see where the track issues are??? I can only go from my background experience to say this was built wrong or needs fixing.

Since these are Alstom Ottawa LRV's that will be running on the line, we have a picture as where those cars stand due to tolerance issues. With the line being straight, there are no curves like Ottawa. other than the 403 WYE area.

We haven't heard anything about tolerance. issues on Finch trackwork and the ties on Hurontario are found all over Europe for LRT's, why issues with Hurontario Trackwork?? I have seen some poor trackwork and it was replaced at a later date..

As for special trackwork issues, the only special trackwork are for switches, diamonds and curve tracks. unless there some thing in the yard and OMSF that I cannot see from the street.

Unless ML has requested changes to the plan as well surprise thing found not in the design drawings along not in the specifications, Mobilinx is responsible to cover the cost of doing things twice or going back after the designer in the UK to cover the cost when there is a big change between 80% and 100% complete drawings where thing have to be rip out and start all over again. Topflight is a good exam example of this where things were done twice due to drawings being wrong..

Not surprised ML hasn't done anything regarding the Loop extension and why Mobilinx when with straight track at Burnhamthorpe than the WYE. What happens down the road as well the cost to put the WYE in, falls on ML shoulders. Same will happen for Steeles Station unless ML comes up with money to cover the extra cost of moving the station to the north side where it should have been on Day One and that can be blamed on Brampton.

There is a photo from Sept 8 where the southbound lanes were torn up as well on Burnhamthorpe and paved as that area was fully repaved last week to open the intersection up. It could have been because the guideway was higher than it was supposed to be, Extra cost for this on Mobilinx shoulders to cover the extra time and cost to do the work.
54063283880_e67b0f705b_b.jpg
 
This is what I have heard as well from someone who is quite privy to the discussions happening behind the scenes. Metrolinx is expecting 100% compliance whereas these contractors (and the people they’ve hired from overseas) are used to wiggle room.
If that's the case then I'm willing to admit that I've misjudged the precipice of this. I still don't like how Metrolinx has strong-armed them, but even less now given the 100% expectation.
 
Still going through some of the shots I took on Monday. Here are a few high shots perhaps some people might find interesting.
Hurontario and Burnhamthorpe.
1729124639252.jpeg

Another one looking north towards the 403
1729124681837.jpeg

I shot this mainly for Edge/Oro Towers but seems applicable here as well:
1729124743504.jpeg

Looking south just north of Central Parkway I think.
1729124826891.jpeg
 

Attachments

  • 1729124585348.jpeg
    1729124585348.jpeg
    255.9 KB · Views: 88
Wow. I just realized the Petro Canada at southwest corner of Burnhamthorpe and Hurontario is gone! Also forgot to mention that it appears that the power station might be under construction at the south east corner of Hurontario and South Service road. I'll try and get a picture of that on the weekend.
 
Wow. I just realized the Petro Canada at southwest corner of Burnhamthorpe and Hurontario is gone! Also forgot to mention that it appears that the power station might be under construction at the south east corner of Hurontario and South Service road. I'll try and get a picture of that on the weekend.
They were removing the last of the foundation on October 11. They been doing trench work on site the last month or it could be ML doing it. No idea why the trench work and can't get close to see what is going on. All the underground fuel equipment was done at the very beginning.

Don't recall seeing any work for the power station at the QEW a week ago unless it is in the loop area for the southbound to go eastbound. Seen crews up there for some tome and assumed it was staging area for the QEW work

As for Edge Tower, they were still not fully at grade a week ago with major rebar work in the south west corner and your photo shows it has been poured. Been too lazy and not interested to walk over and shoot the site as well CP station.

Good close up of the 403 area would be nice to see

Great shots as normal
 
Looks like they did something at the Central Parkway stop (“Fairvew”) and it’s now covered up.

View attachment 605132View attachment 605133
What time did you shoot the site??

After seeing Tim photos, took a walk up to Edge Towers and Central Pkwy station at noon to take a look and a good day for shooting. Was planning on walking home after visiting the 2 sites, but ended up walking over to M City area and Square one shooting various sites.

The sump pump was setup to pour the station platform base with 20% done then. Wasn't sure how late they would be pouring the whole thing, but was 80% done at 4:30 pm. They will be back at a later date to pour the top coat.

Nothing new for Burnhamthorpe stop, other and a trench has been dug from the platform to short of Matthew Gate to build the platform extension curb like CP one.

@Tim MacDonald , I was haft right for Edge Tower per your photos as the south-west area has been poured with the west side below the exiting surface area. The east side not close to being at grade yet. All our projection dates as to when the the site was fully at grade. has been missed by a month or two at this time with more to come.

A few unedited and not tag shots from today as I am still working on Sept 8 shots as I shot over 500 that day.
DSC00598.JPG
DSC00616.JPG
DSC00609.JPG
DSC00626.JPG
DSC00886.JPG
DSC00883.JPG
 
Sept 08
All 516 photos for this day are now on line From PC Station TO Central Pkwy that shows how much work is still to be done going into late 2025 or 2026 before the overhead can be install.

The work south of the North Service Rd is a major problem area, but expect to see 2 lanes of traffic over the winter months for both direction with 1/2 to 3/4 of the southbound curb lane open offering a smoother rider.

Don't know if the the northbound curb lane has open between the Queensway to Dundas as well to Hillcrest. Once that lane is open, Paisley Intersection will be close for 5 weeks to build the guideway across it that was supposed to take place in September and then move up to King St to do the same thing.

By year end, they should be building the Fairview intersection in 2 phases due to the fire station there and any other route will add an extra 3-4 minutes travel time that is not acceptable as well means life or death depending on what they are responding to.

Don't expect Dundas will be done until the summer with John St, Hillcrest, The Queensway fire department and Sherobee intersection done over the winter months. It becomes a guessing game for all intersection from the North service Rd to Where the line will move from the centre to the west side at Mary Fix Creek as well from Topflight to Steeles. One hopes ML change their mind and fund the extra cost to move Steeles Station from the south side to the north side, otherwise we will have another Burnhamthorpe Mess on their hands.

The retaining wall should be close to be finished to allow the southbound curb lane built from Fairview to CP Bridge.
54076959689_e89bc5ac58_b.jpg

54075760587_5ae8363203_b.jpg


Retaining walls being built from the CP to John St to allow the right turning lane and sidewalk shifted west for the LRT station
54076892373_1a6306652e_b.jpg

54076636181_732ea75fc7_b.jpg

54075760672_27e5952a1e_b.jpg
 
a train every 7.5 mins at peak. So if you're lucky as a MCC resident trying to get downtown you will be ideally getting on this LRT with minimal waiting. Then you will be transferring via a walk to Cooksville. The bus got you closer but dont worry this fancy LRT comes around at such reasonable times 7.5mins the speed will more than make up for the old bus parking spot.

If you're a port credit Go Train user do you not get a direct connection to the LRT?
 
If you're a port credit Go Train user do you not get a direct connection to the LRT?
It’s becoming more clear how it will look with complete LRT plus 4 tracks. There will never be one staircase to switch platforms. The LRT will have vertical access to street level only. There will be two island platforms for GO accessed by the existing tunnel.

Based on the GO bridge width, they could l extend one island platform further east towards the LRT, but that would still require stairs to climb over or under the tracks just to the parking area plaza.

Curious to see all these undisclosed plans for this area.
 

Back
Top