News   GLOBAL  |  Apr 02, 2020
 8.5K     0 
News   GLOBAL  |  Apr 01, 2020
 39K     0 
News   GLOBAL  |  Apr 01, 2020
 4.8K     0 

  1. M

    Toronto Toronto | 250 Lawrence West | 35.05m | 9s | Graywood | BDP Quadrangle

    Not at all. The higher floors do not have any of the drywall or finishes completed. I am not sure if any over 5th floor are complete.
  2. M

    Toronto Toronto | 250 Lawrence West | 35.05m | 9s | Graywood | BDP Quadrangle

    Not entirely. Concierge desk still undergoing work.
  3. M

    Toronto Toronto | 250 Lawrence West | 35.05m | 9s | Graywood | BDP Quadrangle

    Here are pics of the lobby from yesterday. Coming together nicely.
  4. M

    250 Lawrence West (Graywood) - Real Estate -

    Builders use the current BoC 1 year rate to calculate interest component of occupancy fees which is 7.84% right now. My client opted to increase down payment by $50k to minimize occupancy and long term mortgage costs. Builder agreed. Went through lawyers to facilitate.
  5. M

    250 Lawrence West (Graywood) - Real Estate -

    It's $150 per day up to 50 days (max $7,500). If you incurred other certain expenses, you may be able to recoup some additional costs.
  6. M

    250 Lawrence West (Graywood) - Real Estate -

    Actually I just got the same. Feb 26th. Hopefully interest rates will be lower then.
  7. M

    250 Lawrence West (Graywood) - Real Estate -

    What makes you think the building will close that quickly? I have seen some close within a few weeks and others months later.
  8. M

    250 Lawrence West (Graywood) - Real Estate -

    How much was the date delayed compared to previously?
  9. M

    250 Lawrence West (Graywood) - Real Estate -

    It is interesting, I have found some builders not dating their revised occupancy letters as a way of trying to protect against paying out the delayed occupancy compensation. I had an unrelated recent experience when I made a claim with Tarion and the builder replied that I was not eligible for...
  10. M

    250 Lawrence West (Graywood) - Real Estate -

    Has anyone received a letter confirming the firm occupancy date for this fall? Wondering if there will a further extension or not.
  11. M

    250 Lawrence West (Graywood) - Real Estate -

    My occupancy is end of November. I am on the 7th floor. Should know by end of August if further delaying. What floor are you on and when in October are you expecting occupancy?
  12. M

    Toronto Toronto | 250 Lawrence West | 35.05m | 9s | Graywood | BDP Quadrangle

    I was at the site yesterday. Tried to talk to one of the contractors. Said he couldn't share anything with buyers. My occupancy is in November and he expresesed confidence that they would be ready by then. I am a little doubtful of that timing. Not sure if anyone else has an earlier occupancy...

Back
Top