crs1026
Superstar
u
You didnt forget about Via, did you?
I think you ought to assume a flyover/under at this location. Four tracks on LSE with the two south tracks feeding the 'under' track to the new double-track northwards. High speed switches are desirable.
- Paul
I show a detail of the LSE Interchange. I am assuming that the LSE can handle 4 tracks. The conflict are shown where trains need to cross other paths - which I haven't really thought if it is workable.
Just West of this interchange, there will be (at peak hour)
RER/SmartTrack
10 Trains per hour from Markham
10 Trains per hour from Malvern
10 Trains per hour from Pickering
total = 2 minute frequency.
GO
5 Trains per hour from Markham
3 Train per hour from North Pickering
10 LSE GO Trains (maybe a high estimate)
total = 3+ minute frequency.
You didnt forget about Via, did you?
I think you ought to assume a flyover/under at this location. Four tracks on LSE with the two south tracks feeding the 'under' track to the new double-track northwards. High speed switches are desirable.
- Paul