denfromoakvillemilton
Senior Member
About time.
Next up - Brampton and fill in the gaps on the Stouffville and Barrie.
Next up - Brampton and fill in the gaps on the Stouffville and Barrie.
About time.
Next up - Brampton and fill in the gaps on the Stouffville and Barrie.
I'm not sure about what was promised back in the day, but with the GO Expansion Business case there really isn't anything about all day service to HGC.I recall RER initially was to include all day service to the Hamilton GO Centre. Is this an indication that is no longer going to happen? West Harbour's location is slightly less convenient with respect to downtown, LRT connection, etc. Has WH been chosen over HGC because of issues with CPR?
Ok thanks. Glad to hear. I think KW will be the biggest challenge. Although if this is an indication, CN maybe be more flexible than thought at first.Contra-flow services in rush hour should be plausible on Stouffville now, I think.........but @smallspy would likely know better.
Barrie, and K-W will likely need a round of track projects completed before that happens.
I think K-W weekend service is likely the next big addition.
I also would not be surprised to see 15M service on Lakeshore during peak-weekend times.
Contra-flow services in rush hour should be plausible on Stouffville now, I think.........but @smallspy would likely know better.
Stouffville (Mount Joy, to be more precise) is nowhere near ready. I would say maybe next spring.
- The second track is still being ballasted north of Kennedy
- Agincourt and Milliken stations are progressing, but nowhere near ready for two track operation
- The two creek bridges are still far from completion
- There are gaps in the second track in various locations
- Passing track at Mount Joy is still in procurement
- Crossovers south of the 401 are in place but signalling not cut in
- Paul
www.thepublicrecord.ca
My impression is that the contract to double the track was let in a hurry, before anyone had really digested what the station requirements would be. At Milliken, a fair bit of second track with new concrete ties was laid and surfaced southwards from Steeles towards McNicholl - .... and then the segment through the station was torn up, when the tunnelling for the station work started. It never saw a train.I was only assuming contra-flow to Unionville; that said; even that clearly seems even that is out-of-reach, for now.
Though, I don't see why the project isn't further along at this point.
What makes you so sure of this? According to Metrolinx, Off peak ridership actually increased during COVID because people now want to travel at times where trains aren't congested, and are likely to reach work during off peak times in case they need to come in for something. Furthermore, suburbanites have a benefit for using regional rail even when Highways aren't congested. Ignoring the fact that we are reaching the point where certain highways like DVP and Gardiner are congested even during off peak times, sometimes being able to park for free at a station like West Harbour and taking the train downtown is far more convenient than driving all the way downtown and paying $5 for parking, not to mention far cheaper. The only situation where the train won't be more viable is if you're travelling in a group, where driving is probably going to be cheaper, or if your destination isn't downtown but on some weird orbital ring around it, and transfering from train to train seriously adds to the travel time.All day service to Hamilton is certainly nice to have but I don't think it will really get much ridership and due to this, it could start bleeding funds from other services.