Do you have any concrete reason to think it'll take four years, or is that just speculation?
Im going from what they managed to build this summer which is only one side of the street on 2 blocks. I know that some utility work needed to get done and this is besides that work.
 
“They are still building.”

Yes, they are. I am liking the finished product (at least those few blocks that are finished) but the proof of the pudding will be in how they are maintained and what they look like a few years after completion.

Having said that, from start to completion by the time they get to 124 Street, the construction of just this phase of Jasper Avenue’s upgrading will have taken longer to complete than it took to twin the Trans Mountain Pipeline all the way from Edmonton to Burnaby..
 
20250927_171345.jpg


20250927_171501.jpg


20250927_171548.jpg



NE corner at Jasper/116 St - staging area

20250927_171630.jpg


20250927_171655.jpg


20250927_171755.jpg


20250927_172031.jpg


20250927_172103.jpg


20250927_172151.jpg


20250927_172200.jpg


20250927_172416.jpg


20250927_172440.jpg


20250927_172458.jpg


20250927_172702.jpg


20250927_172708.jpg


continued in next post
 
Can someone explain picture #2 above, where they have the asphalt on the concrete around the drain? That can't be finished, right?

Also, gas at 134 downtown? Eeek.
Those are usually a temporary solution when the road isn't at final grade yet but is opened up, it protects the concrete that juts out for the drain. Helps with not being damaged by cars driving over the hard edge (both the cars tires, and the concrete itself). Once final grade is laid, it would be flush.
 
Those are usually a temporary solution when the road isn't at final grade yet but is opened up, it protects the concrete that juts out for the drain. Helps with not being damaged by cars driving over the hard edge (both the cars tires, and the concrete itself). Once final grade is laid, it would be flush.
One lift of asphalt for a year or two - lets any settlement show - then top lift of asphalt levels out any of that minor settlement. Or they might do top lift over the whole width of the road this year, after they have finished bottom lift on the south side.
 
So in that photo I referenced, they will lay the asphalt on top of the cement?
Ah, yes, from the photo it looks like concrete. I'm assuming the concrete is there because it's a bus stop location and needs the better base. One lift of asphalt to go on top of the concrete and up flush with the curb and gutter. My best guess.
 
One lift of asphalt for a year or two - lets any settlement show - then top lift of asphalt levels out any of that minor settlement. Or they might do top lift over the whole width of the road this year, after they have finished bottom lift on the south side.
A year or two? Do you think Walterdale Hill Road might get that last lift before we lose the base layer and sub base?