In July 2021, the City’s contractor encountered unforeseen utility conflicts at the KQQR intersection during excavation for new pole installations. In order to ensure safety and to resolve the conflicts work was paused. This delayed to the start of Stage 2 work to November 13, 2021.
At the present time, the City’s contractor is working on The Queensway (west of Sunnyside Avenue) towards Parkside Drive, which the east limit of the work zone. Crews are also finalizing work on King Street West (south of Queen Street West) to approximately 100 metres further south and at the KQQR intersection proper.
Previous delays, combined with some periods of adverse fall/winter weather, COVID-19 related labour shortages and supply chain issues have deferred completion of Stage 2 work (KQQR intersection, The Queensway and King Street West) to September 3, 2022.