cyruskafaiwu
New Member
NEWS NEWS NEWS! READ ALL ABOUT IT!
link for images: http://www.confederationline.ca/construction/construction-update-6/
link for images: http://www.confederationline.ca/construction/construction-update-6/
Girder installation at Hurdman Bridge continues / La mise en place des poutres de pont au pont Hurdman continue
Preston Street detour / Déviation de la rue Preston
Booth Street Closure
Booth Street, north of Albert Street has been closed to allow for the construction and installation of the LeBreton Flats Diversion Chamber scheduled this winter. The temporary Preston Street Extension was built to provide a detour during Booth’s closure.
Lyon Station cavern works continue / Les travaux du grand espace souterrain de la station Lyon se poursuivent
Lyon Station Cavern
Lyon Station cavern reinforcement is ongoing and includes construction of L-walls.
Parliament Station cavern waterproofing / Imperméabilisation du grand espace souterrain de la station Parlement
Parliament Station Cavern
Parliament Station cavern reinforcement is ongoing. Other activities include backfilling, waterproofing, and concrete pouring.
Shotcrete works in the Rideau Station cavern / Application de béton projeté dans le grand espace souterrain de la station Rideau
Rideau Station Cavern
Tunnel reinforcement continues with shotcrete and rockbolt installation. Works to relocate Jawbreaker to the East Portal are ongoing. Excavation of the bench is planned to begin later this month.
Basement of the Scotiabank building / Sous-sol de l’édifice de la Banque Scotia
Rideau Station
Exterior demolition of the existing Scotiabank building continues at the future location of the Rideau Station entrance (east).
Final works at the Rideau pedestrian footbridge / Derniers travaux à la passerelle pour piétons Rideau
Rideau Pedestrian Footbridge
Final works to reinforce the Rideau pedestrian footbridge have been completed.
Construction of interior components of the Belfast Yard Administration and Maintenance Building / Construction des éléments intérieurs de l’édifice de l’administration et de l’entretien de la Cour Belfast
Belfast Yard Administration and Maintenance Building
Masonry work, cladding and panel installation continue for the building envelope. Construction of the internal components progresses and includes pouring of concrete slabs. Roofing continues on the shed.
Works on the Belfast Yard connector / Travaux au tunnel de raccordement de la Cour Belfast
Belfast Yard Connector
Works on the Belfast Yard connector, which allows vehicles to travel to and from the Light Rail Transit (LRT) track to Belfast Yard, are ongoing, and include rebar installation and pouring of the concrete bases and walls. Rockbolt installation for bridge’s piles continues.
Drilling for the installation of concrete caissons north of the existing Hurdman Station / Forage en vue de l’installation de caissons en béton au nord de la station Hurdman actuelle
Hurdman Station
Elevated guideway work continues with caisson drilling over the next week north of the existing Hurdman Station.
Highway 417 median near Vanier Parkway / Terre-plein de l’autoroute 417 près de la promenade Vanier
Highway 417 Roadworks
Installing electrical and light poles, and sewer works continue from Cyrville Road to Nicholas Street.
Lees Avenue underpass / Passage souterrain de l’avenue Lees
Lees Avenue Underpass
General site cleanup continues.
Girder installation at Hurdman Bridge continues / La mise en place des poutres de pont au pont Hurdman continue
Hurdman Bridge
Mobilisation and girder installation, part of the reconstruction of the bridge’s median span, is ongoing as preparations begin for the installation of the underdecking.
Concrete crushing at Vanier Parkway staging area / Concassage de béton à la plateforme de travail de la promenade Vanier
Vanier Parkway Overpass
Crushing of the old bridge’s structure continues at the staging area.
Final works continue at the Coventry Pedestrian Footbridge / Travaux finals à la passerelle pour piétons Coventry
Coventry Pedestrian Footbridge
Works continue in anticipation of substantial bridge completion at the end of the month and include the ceiling’s plumbing conduits, roof vent installation, and concrete pouring and panel installation of stairs.
Upcoming Construction Activities
In the coming weeks, the following construction activities will advance:
Preparatory works for the Booth Street Bridge will begin.
The roof of the Belfast Yard shed is scheduled for completion mid-winter.
Lyon Station west entrance excavation is anticipated to begin late winter.
Parliament Station utility relocation works on Queen Street are scheduled this winter.
Parliament Station west entrance is scheduled to begin late winter.